safety in construction
Standard
number
title
Raft foundations:
End bearing piles:
Friction piles:
Settlement reducing piles:
Tension piles:
Laterally loaded piles:
Piles in fill:
SAFETY
IN
CONSTRUCTION
S.NO
CONTENTS PAGE NO
UNIT-I
1 GENERAL SAFETY
CONSIDERATION 3
2 ANALYZING
CONSTRUCTION JOBS FOR SAFETY 4
3 CONTRACT DOCUMENT 5
4 EXCAVATION 7
5 FOUNDATION 9
6 DEMOLITION 10
7 DISMANTLING 14
8 TYPES OF FOUNDATIONS 14
UNIT-II
1 SAFETY IN ERECTION 22
2 CONSTRUCTION MATERIALS 22
3 SAFETY IN TYPICAL
CIVIL STRUCTURES-DAMS 23
UNIT-III
1
LOCK OUT OF MECHANICAL AND ELECTRICAL 25
MAINTENANCE
2 HAND TOOLS 27
ABBREVIATIONS
UNIT-I
1. GENERAL SAFETY CONSIDERATION
v Common
tools such as hammers, utility knives, staple guns, ladders, rakes and power
tools must be handled with care.
v More
complicated equipment such as blowers, foamers and sprayers require special
instruction and practice.
v Have
a first aid kit and a fire extinguisher handy and know how to use them.
v Protect
your back when lifting heavy objects, do not lift and reach at the same time.
v Take
special care when handling heavy (or) bulky objects, especially when going up
and downstairs and ladders.
v Smoking
is especially hazardous. Do not take smoke breaks near insulation (or) fumes.
v Keep
your work site well organized, with tools out of the way of traffic, and give
yourself plenty of clear space to manoeuvre.
v Make
sure that the work space is well lighted and ventilated.
v Ensure
proper electrical supply for power tools.
v Wear
appropriate protective clothing for the job at hand.
v Do
not work in an attic on a hot day. Heat stress can cause accidents and serious
illness.
v Maintain
a clean work area and separating it from the place will minimize exposure to
materials.
v Keep
fibrous materials and materials that generate vapours well sealed until they
are needed, and close them in containers at the end of the work day.
v Vaccum
the work area daily to remove fibres and dust.
v Take
particular care when you work with insulation and other particulate materials,
plastic insulation and caulking, and always follow the recommended safety
procedures for working with specific materials.
v Long
sleeves, tight cuffs and loose, thick clothing will help minimize any skin
irritations.
v Special
barrier creams that protect the skin of people working with fibrous materials
are available from safety supply houses.
v Wear
goggles wherever there is any possibility that insulation dust will come in
contact with the eyes.
v Wear
a mask for non-toxic particles if there is a possibility of breathing air borne
particles of insulation material.
v Wear
a well designed snug-fitting face mask respirator with a particulate filter
when handling glass fiber, mineral wool (or) cellulose fibre insulation.
v Wear
a hard hat to prevent head injuries and to protect hair from insulation
particles.
v To
prevent falls, passage ways and work areas should be kept orderly, and dry and
slip-resistant materials should be in place.
v Spills
should be cleaned up immediately.
v Guard
rails should be provided where walk ways are elevated.
2.
ANALYZING
CONSTRUCTION JOBS FOR SAFETY
v Construction
involves many hazardous activities.
v While
earning great wages, construction workers risk injury when working due to their
work with dangerous mechanical equipment, electrical equipment, hazardous
chemicals and heights.
v To
ensure that effective safety procedures are implemented, construction job
safety analysis specialists analyze the processes of the construction job and
create methodologies to ensure that hazards are avoided.
Function:
v Construction
job safety analysis specialists study a construction site in order to make sure
that the site is safe.
v They
must be aware of both the nature of the construction site such as the
environmental conditions and of what will be constructed and how that will be
constructed.
v They
must identify all the potential hazards and then develop a set of procedures in
order to help the workers avoid these hazards.
v The
method of hazard control must be communicated effectively to the workers
through both oral and written communication.
v Construction
job safety analysis specialists must also be aware of the ergonomics of work in
the particular construction site.
Conditions:
v These
specialists spend time outdoors analyzing construction sites, including sites
that have significant hazards.
v They
are not as exposed to construction hazard as the construction workers.
v They
also spend time in an office communicating with various safety departments.
Skills:
v Construction
job safety analysis specialists must be aware of state regulations regarding
construction safety.
v They
must be flexible and able to work under pressure.
v Construction
workers are more at risk for on the job injuries and fatalities than workers in
most other industries.
v According
to the U.S. department of labor, masonry demolition workers are at risk from
hazards that arise as a result of deviations.
Job safety analysis checklist:
v Job
safety analysis is all about evaluating the work environment to determine what
types of hazards exist.
Construction site safety checklist:
v Construction
workers face numerous dangers on the job site, such as collapsing scaffolds,
head injuries, electrocution and falls.
v To
make sure that everyone is aware of what is going on, JSA’s and safe work
method statements are used in building and construction as a way to assess what
hazards may
v come
upon the job and deal with them safely.
v Jobs
that are more dangerous than usual like working at heights, near electricity (or)
working equipment.
v These
jobs are classified as high risk work:
Ø
Many construction injuries result from
operational errors.
Ø
JSA was developed at construction sites
the physical environment is constantly changing workers move through the site
in the course of their work, they are often endangered by activities performed
by other teams.
Ø
To address this difficulty a structured
method for hazard analysis and assessment for construction activities called
construction job safety analysis (CJSA) was developed.
Ø
The method was developed within the
framework of research toward a lean approach to safety management in
construction, which required the ability to predict fluctuating safety risk
levels in order to support safety conscious planning and pulling of safety
management efforts to the places and times where they are most effective.
3. CONTRACT DOCUMENT:
ü The
contract documents are one of the most important pieces that will guarantee of
a successful project.
ü This
list contains the most common documents that must form part of every
construction contract.
ü In
addition to this list, there are numerous contract support documents that can
be used in combination with the standard documents. For example:
§
Instruction forms
§
Time extension claim
§
Request for information
§
Preliminary building agreement
§
Progress payment certificate
§
Practical completion notice
§
Defects document
§ Contract
information statement
Other documents:
1) Agreement
The
agreement to be used by the contracting officer (owner) and the contractor. The
most essential part of the contract documents.
2) General
conditions
This
contract document will define the obligations and rights on how to execute the
project.
3) Special
conditions
This
is usually an extension of the contract and to the general conditions. This
part must specify specific conditions and clauses to each particular project (or)
job.
4) Bill
of quantities
This
is formed by the list of diverse trades, and materials included that form part
of the construction. Sometimes this document is not required by the contracting
officer.
5) Drawings
All
set of drawings that form part of the job to be performed. These drawings are
usually the latest drawings and must be received by the contractor prior to the
date of commencement. It must include all drawings from consultants and will
constitute the entire project being contracted.
6) Specifications
The
technical requirement to complete, execute and/or perform every little task (or)
material being incorporated in the construction projects. It will add
intelligence to the construction drawings, specify common standards, deviations
accepted, materials accepted and the required testing for all materials. Usually
specifications are composed by referencing construction standards and codes.
7) Schedules
The
construction schedule is an important piece of the document. In this part, the
contractions will require updated schedules throughout the construction
progress, and might form part of the monthly, or agreed term, application for
payments.
8) Pricing
schedules
Breakdown
of all items being incorporated in the construction project. This is usually
the base of the application for payment. It can be detailed per item (or) in a
lump sum form, not specifying individual items.
9) Insurances
This
part will be essential part of the contracting officer, since it will provide
the guarantee to the owner that the contractor has the means and the economic
backup to perform the construction contract. It will include specific types of
coverage’s required bending, and all insurance protections to the owner, the
contractor and third parties.
Ø The
contract documentation relates to all pre-tender, tender and contractual
documentation.
Ø Contract
documentation provides builders with sufficient information to be able to
construct required works to meet the service delivery requirements.
4.
EXCAVATION
v Establish
the locations of underground and overhead utilities and services before
beginning excavation.
v Contact
utility companies and advise them prior to the start of excavation.
v Super
imposed loads like mobile equipment working close to the excavation edges
require extra sheet piling, brazing.
v The
use of mobile equipment near excavation also require substantial barricades (or)
stop logs.
v A
competent person must take ongoing daily inspections of excavations, the
adjacent areas and protective systems, including after every rainfall or other
hazard producing occurrence.
v Walkways
are required to cross over excavations.
v Walkways
(or) bridges over excavations greater than 4 feet in depth require standard
guardrails.
v Backfill
excavations upon completion.
v Have
a registered professional engineers design sloping(or)benching for excavations
greater than 20m feet depth.
Reference:
OSHA
1926 SUBPART P -Excavations cope
application
29
CFR 1926.650 and
definition
1926.651 -Specific
excavation requirements
What you need to do?
Ø The
law says you must prevent danger to workers in or near excavations.
Ø To
maintain the required precautions, a competent person must inspect excavation
supports (or) battering at the start of the working shift and at other
specified times.
Ø No
work should take place until the excavation is safe.
Ø Commercial
clients must provide certain information to contractors before work begins.
This
should include relevant information on:
·
Ground conditions.
·
Underground structures (or) water
courses.
·
The location of existing services.
· This
information should be used during the planning and preparation for excavation
work.
Key issues are:
Ø Collapse
of excavations.
Ø Falling
or disloding material.
Ø Falling
into excavations.
Ø Inspections.
What you need to know?
ü Every
year people are killed (or) seriously injured by collapses and falling
materials while working in excavations. They are at risk from:
·
Excavations collapsing and burying or
injuring people working in them.
·
Material falling from the sides into any
excavation.
·
People (or) plant falling into
excavations.
ü Trenchless
techniques should always be considered at the design stage as they replace there
for major excavations.
Ø Collapse of excavations:
v Temporary
support-Before digging any trench pit, tunnel, or other excavations, decide
what temporary support will be required and plan the precautions to be taken.
v Make
sure the equipment and precautions needed are available onsite before the work
starts.
v Battering
the excavation sides-Battering the excavation sides to a safe angle of repose
may also make the excavation safer.
v In
granular soils, the angle of slope should be less than the natural angle of repose
of the material being excavated. In wet ground a considerably flatter slope will
be required.
Ø Falling(or)dislodging material:
v Loose
materials-May fall from spoil heaps into the excavation. Edge protection should
include boards (or) other means, such as projecting trench sheets (or) box sides to protect against falling materials. Head
protection should be worn.
v Undermining
other structures-Check that excavations do not undermine scaffold footings,
buried sources (or) the foundations of nearby buildings (or) walls. Decide if
extra support for the structure is needed before you start. Surveys of the
foundations and the advice of a structural engineer may be required.
v Effects
of plant and vehicles-Do not park plant and vehicles close to the sides of excavations.
The extra lodgings can make the sides of excavations more likely to collapse.
Ø Falling into excavations:
v Prevent
people from falling-Edges of excavations should be protected with substantial
barriers where people are liable to fall into them.
v To
achieve this use
·
Guard rails and toe boards inserted into
the ground immediately next to the excavation side, or
·
Fabricated guard rail assemblies that
meet the sides of the trench bore.
·
The support system itself eg.using
trench box extensions (or) trench sheets longer than the trench depth.
Ø Inspection:
v A
competent person who fully understands the dangers and necessary precautions
should inspect the excavation at the start of each shift.
v Excavations
should also be inspected after any event that may have affected their strength (or)
stability, or often a fall of rock or earth.
v A
record of the inspections will be required and any faults that are found should
be corrected immediately.
ü Newyork
court of appeals, Cornell university law school, legal information institute (1992,
Oct 29).
ü This
newyork case determined that safety precautions during excavation operations
are not limited to building sites.
5.
FOUNDATION
v Foundation
also called a groundsill is a structure that transfers loads to the earth.
v Foundations
are designed to have an adequate load capacity with limited settlement by a
geotechnical engineer, and the foundation itself is designed structurally by a
structural engineer.
v If
the foundation is strong then it can withstand severe shocks and other
problems, but if the foundation is weak (or) loose then we may land up into
serious trouble.
v Foundations
that have either concrete strip footings and pads (or) a concrete slab will
form the foundation and floor of the new home.
v The
general class type of soils when foundations are considered is as follows:
Ø Foundation
is as important as any other element of your structure.
Ø The
foundation is the first piece of a home to be constructed and creates a base
for the rest of a component.
Ø To
create the foundation wall, mortar is used between blocks to hold them together
forming the wall.
Ø Insulated
concrete forms (ICFs) are common in regions in which the local building code
requires the foundation to be insulated.
6.
DEMOLITION
v Demolition
work involves many of the hazards associated with construction.
v However
demolition incurs additional hazards due to unknown factors such as:
Ø Deviations
from the structure’s design introduced during construction, approved or
unapproved modification that alerted the original design, materials hidden
within structural members, and unknown strengths (or) weaknesses of
construction materials.
Ø To
counter these unknowns, all personnel involved in a demolition project must be
fully aware of these types of hazards and the safety precautions to take to
control the hazards.
Ø Demolition
hazards are addressed in specific standards for the general and construction
industries.
What you need to do?
v The
law says that all demolition work should be carefully planned and carried out
by competent people (or) practioners to avoid unplanned structural collapse.
Arrangements for demolition:
v Demolition
arrangements should be written down before the work begins.
v This
safe system of work maybe in the form of a safety method statement identifying
the sequence required to prevent accidential collapse of the structure.
v Establishing
exclusion zones when using explosives in demolition CIS 45.
Key issues are:
v Falls
from height.
v Injury
from falling materials.
v Uncontrolled
collapse.
v Risks
from connected services.
v Noise
and vibration.
What you need to know?
v A
systematic approach to demolition projects is a team effort between many
people, who all have responsibilities:
Ø Clients
must appoint duty holders who are competent and adequately resourced
Ø Structural
engineers survey the site and assess the stability of nearby structures the
risks of uncontrolled collapse, and the risks from hazardous materials. This
should be done before work begins and not be left for the principal contractor
to organize.
Ø CDM
coordinators plan effective site management that keeps people (site workers and
the public) as far as possible from the risks. They should give principal
contractors as much information as possible.
Ø Principal
contractors coordinate and manage health and safety issues during the
demolition project.
Ø Site
managers supervise workers and ensure they are following safe working practice.
Ø Subcontractors
and site workers must understand and follow the precautions and ensure that
their colleagues do too.
Falls from height:
v During
demolition workers can be injured falling from edges, through openings, fragile
surfaces and partially demolished floors.
v Duty
holders have a responsibility to assess eliminate and control the risks of
falls from height.
Injury from falling materials:
v Workers
and passers-by can be injured by the premature and uncontrolled collapse of
structures, and by flying debris.
v A
safe system of work is one that keeps people as far as possible from the risks.
This may include:
Ø Establishing
exclusion zones and hard hat areas clearly marked and with barriers if
necessary.
Ø Covered
walkways.
Ø Using
high reach machines.
Ø Reinforcing
machine cabs so that drivers are not injured.
Ø Training
and supervising site workers.
Uncontrolled collapse:
v The
structural survey should consider
Ø The
age of the structure
Ø Its
previous use
Ø The
type of construction
Ø Nearby
buildings (or) structures
Ø The
weight of removed material(or)machinery on floors above ground level
v The
method statement for the demolition should identify the sequence required to
prevent accidential collapse of the structure.
Risks from connected services:
v Gas,
electricity, water and telecommunications services need to be isolated (or) disconnected
before demolition work begins.
v If
this is not possible, pipes and cables must be labeled clearly, to make sure
they are not disturbed.
Vibration:
v Vibration
hand tools used in demolition can cause hand arm vibration syndrome(HAVS).
v Workers
exposure to vibrating needs to be assessed and managed.
Standards:
v This
section highlights OSHA standards, standard interpretations (official letters
of interpretation of the standards), and national consensus standards related
to demolition.
Ø 1926
Subpart T. Demolition
Ø 1926.850
Preparatory operations
Ø 1926.851
Stairs, passage ways and ladders
Ø 1926.852
Chutes
Ø 1926.853
Removal of materials through floor openings
Ø 1926.854
Removal of walls, masonry sections, and chimneys
Ø 1926.855
Manual removal of floors
Ø 1926.856
Removal of walls, floors, and material with equipment
Ø 1926.857
Storage
Ø 1926.858
Removal of steel construction
Ø 1926.859
Mechanical demolition
Ø 1926.860
Selective demolition by explosives
Standard interpretations:
v Application
of the asbestos standard to demolition of buildings with ACM in place (2002,
August 26).
v OSHA
standards addressing reverse signal alarms on excavators (1995, May 10).
v Demolition
regulations do apply to the removal of ceilings and interior non-load bearing
walls and partitioners (1994, January 27).
v 1926.850
demolition work and the use of clamshells (1974,September 17).
v Classification
of 29CFR 1926.855(b) and (f) (1979,July 5).
v American
national standards institute (ANSI) A10:6-1983 Safety requirements for
demolition operations.
Hazards and solutions:
v Before
starting a demolition the person (or) persons incharge of the demolition should
be adequately prepared for the task with regard to the health and safety of the
workers.
v These
preparatory operations involve the overall planning of the demolition job,
including the methods to be used to bring the structure down, the equipment
necessary to do the job, and the measures to be kept to perform the work safely.
OSHA Technical Manual (OTM):
v 1999
January 20.
v OSHA
directive TED 01-00-015-[TED 1-0.15A].
v Demolition-Include
information on preparatory operations, special structures demolition, and safe
blasting procedures.
Newyork
court of appeals, Cornell university law school, legal information (1992, out
29).This newyork case determined that safety precautions during demolition
operations are not limited to building sites.
Construction industry safety and
health outreach program OSHA 1996 May:
v Demolition-Describes
safety regulations for demolition, such as preliminary operations, engineering
survey, utility location, medical services, first aid, fire prevention and
protection, special structures demolition and safe blasting procedures.
Demolition services provided
include the following:
v Explosive
and structural demolition services for commercial, industrial and government
projects.
v Selective
demolition (or) strip out work.
v Industrial
demolition and dismantling services.
v Emergency
demolition services.
Ø Demolition
is the tearing down of buildings and other structures. Demolition contrasts
with deconstruction, which involves taking a building apart while carefully
preserving valuable elements for reuse.
Ø The
building is pulled down either manually (or) mechanically using large hydraulic
equipment:
ü Cranes
ü Excavators(or)bulldozers
Ø The
tallest building demolished by non-terrorist methods.
Ø Before
any demolition activities, there are many steps that need to take place
including but not limited to performing asbestos abatement, removing
hazardous(or)regulated materials, obtaining necessary permits, submitting
necessary notifications, disconnecting utilities and development of
site-specific safety and work plans.
Ø The
demolition project manager/supervisor will determine where undermining is
necessary so that a building is pulled in the desired manner and direction.
Ø Safety
and cleanup considerations are also taken into account in determining how the
building is undermined and ultimately demolished.
Ø Hoe
rams are typically used for removing the concrete road deck and piers during
bridge demolition, while hydraulic shears are used to remove the bridge’s
structural steel.
Ø In
some cases a crane with a wrecking ball is used to demolish the structure down
to a certain manageable height.
Ø However
crane mounted demolition balls are rarely used within demolition due to the
uncontrollable nature of the swinging ball and the safety implications
associated.
Ø High
reach demolition excavators are more often used for tall buildings where
explosive demolition is not appropriate (or) possible.
Ø To
control dust, fire hosed is used to maintain a wet demolition.
Ø Rotational
hydraulic shears and standard reinforced bucket attachments are common
demolition tools.
7. DISMANTLING:
v The
law says that all dismantling work should be carefully planned and carried out
by competent people to avoid unplanned structural collapse.
8.
TYPES
OF FOUNDATIONS
There
are three types of foundations that are commonly used in the US.
Full height basements:
v It
is an accessible space between the soil and the bottom of the first floor.
v It
usually has more headroom than a crawl space.
v This
construction is predominant in cold climates where the foundation needs to be
situated below the frost level.
Crawl space:
v A
crawl space is an accessible space with limited headroom, typically between the
soil and the bottom of the first floor.
v This
construction is predominant in areas where there is heavy clay content in the
soil.
Slab on grade:
v Slab
on grade is a type of foundation consisting of a structural concrete slab
poured directly on the grade.
v No
accessible space exists in slab-on-grade construction.
v Slab
on grade foundations are popular in areas where there is a high water table.
v All
three types of building foundation are usually constructed out of poured
concrete, but can also use concrete masonry units (or) insulated concrete forms.
Types:
Natural foundations:
v It
is the name applied to such as are formed on the soil itself, and it is
applicable when the soil is practically in compressible.
v If
the site be fairly level it is only necessary to make it thoroughly so all
loose and decayed portions being cutaway and failed up with cement concrete.
v Sometimes
fissures occur which, if not too deep, must be filled up with concrete (or)
spanned by an arch.
v If
the site is on a slope (or) in a hollow the loose and decayed portions are cut
away and a series of blasts made where the walls are designed to come.
v The
holes formed thereby are filled with concrete, which is then benched up into
level steps, upon which the walls are raised.
v The
object of the blasting is to roughen the surface and thus prevent the concrete
from sliding.
v If
the soil is likely to be shaken by blasting, then the soil itself must be cut
into steps.
v A
drain must always be cut from the lowest point in the benching to prevent the
foundation from becoming water-logged.
v When
the foundation is benched the walls must be brought up level with large stones
with fire bed joists as otherwise the settlement of the more numerous joists in
the deeper trenches will cause unsightly cracks to appear in the super structure.
Artificial foundations:
v It
is the term applied to any artificially formed support for a building, and may
be classified as:
Ø Spread
foundation
Ø Pile
foundation
Ø Pier
foundation
v Spread
foundations is the name given to foundations used for buildings upon compressible
soil.
v These
consequently require to extend considerably on each side of the walls, so as to
reduce the bad per square inch to that which will be safely bome by such soils.
v Foundations
of this class are formed of concrete (or) large stores and sometimes of wood.
Concrete foundations:
v For
small buildings (or) comparatively firm ground concrete foundations are almost
invariably used for important work the depth (or) width is rarely calculated,
the width being simply made wide enough on each side of the footing to give a
man foot-room to work in and the depth is made at least equal to the thickness
of the wall.
v The
footings are usually stepped out to the width of the wall on each side.
Ø Types of concrete foundations:
ü There
are many variations of concrete slabs depending on the purpose of the slab.
ü Below
are some useful links for understanding concrete foundations, along with the
three types of concrete foundations.
Ø T-shaped:
ü A
traditional foundation method to support a structure in an area where the ground
freezes.
ü A
footing is placed below the frost line and then the walls are added on top.
ü The
footing is wider than the wall, providing extra support at the base of the
foundation.
ü T-shaped
foundations are used in areas where the ground freezes.
ü First
the footing is placed.
ü Second
the walls are constructed and poured.
ü Lastly
the slab is placed.
Ø Slab
on grade foundation:
ü As
the name suggests, a slab is a single layer of concrete, several inches thick.
ü The
slab is poured thicker at the edges, to form an integral footing, reinforcing
rods strengthen the thickened edge.
ü The
slab normally rests on a bed of crushed gravel to improve drainage.
ü Casting
a wire mesh is the concrete reduces the chance of cracking.
ü A
slab on grade is suitable in areas where the ground doesnot freeze, but it can
also be adapted with insulation to prevent it from being affected by the frost
heaves.
· Slab
on grade used in areas where ground doesnot freeze.
· The
edges of the slab on grade are thicker than the interior of the slab.
· The
slab on grade is monolithic (poured all at one time).
Ø Frost protected:
ü This
method only works with a heated structure.
ü It
relies on the use of two sheets of rigid, polystyrene insulation.
ü One
on the outside of the foundation wall and the other laid flat on a bed of
gravel at the base of the wall to prevent freezing, which is a problem with
slab on grade foundations in areas with frost the insulation holds from the
structure in the ground under the footings and prevents heat loss from the edge
of the slab.
ü This
heat keeps the ground temperature around the footings above freezing.
· Only
works with a heated structure.
· Has
the benefits of a slab on grade method(concrete poured monolithically) in areas
subject to frost.
· Concrete
is poured in one operation, versus 3 pours required for T-shaped foundations.
Shallow foundations:
v Shallow
foundations (sometimes called spread footings) include pads(isolated footings),
strip footing and rafts.
Ø Pad
foundations
Ø Strip
foundations
Ø Raft
foundations
v Shallow
foundations are those founded near to the finished ground surface: generally
where the founding depth (Df) is less than the width of the footing and less
than 3m.
v These
are not strict rules, but merely guidelines.
Ø Basically,
if surface loading (or) other surface conditions will affect the bearing
capacity of a foundation it is ‘Shallow’.
Ø Shallow
foundations are used when surface soils are sufficiently strong and stiff to
support the imposed loads; they are generally unsuitable in weak or highly
compressible soils, such as poorly-compacted fill, recent lacustrine and
alluvial deposits etc.
ü Pad foundations:
v Pad
foundations are used to support an individual point load such as that due to a
structural column.
v They
may be circular, square (or) rectangular.
v They
usually consist of a block (or) slab of uniform thickness, but they may be
stepped (or) launched if they are required to spread the load from a heavy
column
v Pad
foundations are usually shallow, deep foundations can also be used.
v This
is where isolated columns(pillars) are casted from the foundation to carry a
slab at the top of the ground.
v This
is mostly used when you want to make use of the under of buildings as parking
space (or) when the other space is not conducive to have foundation.
v Build
a house across a flowing stream and you want a situation where you can see your
boat to pass under the building because the stream is under.
v Then
you may not need to dig foundation that will cut across the river but by
applying columns (pillars) at the edge of the river like a bridge, this columns
are thus isolated and there foundations are referred to as pad.
Ø Strip foundations:
v Strip
foundations are used to support a line of loads either due to a load bearing
wall, or if a line of columns need supporting where column positions are so
close that individual pad foundations would be inappropriate.
v This
is the most common type, it is mainly used where you have strong soil base and
non-water logged areas.
v Most
small buildings of just a floor are constructed with this type of foundation.
v Depends
on the structural engineers recommendation, the depth of your foundation could
be from 600mm to 1200mm mostly for small scale buildings.
v When
the soil is excavated, a level at which the concrete is poured this may be from
150mm(6’’) thick to 450mm(18’’) thick depending also on building after that
block is set round the trenches at the center of foundation, the foundation
usually follows the block lines.
v The
blocks are then layed to d.p.c level before another concrete is poured on top,
this is the german (or) oversite concrete.
v This
type seems to be the cheapest.
v Raft
foundations are used to spread the load from a structure over a large area,
normally the entire area of the structure.
v They
are used when column loads (or) other structural loads are close together and
individual pad foundations would interact.
v A
raft foundation normally consists of a concrete slab which extends over the
entire loaded area.
v It
may be stiffened by ribs (or) beams incorporated into the foundation.
v Raft
foundations have the advantage of reducing differential settlements as the
concrete slab resists differential movements between loading positions.
v They
are often needed on soft (or) loose soils with low bearing capacity as they can
spread the loads over a larger area.
v This
is where you have concrete spread around your building from the base of
foundation all through to the german floor/oversite concrete/ground floor slab.
v It
is mainly used in areas where the soil are sandy and loose, you spend more on
tall through to the german floor/oversite concrete/ground floor slab.
v It
is mainly used in areas where the soil are sandy and loose, you spend more on
this than the other previous two most of the time.
v It
is also recommended in water logged areas but with buildings of less storage.
v It
has a ground beam which shuts out from the foundation base and is also attached
to the attached to the ground floor slab to form a network of concrete embedded
round the building space.
v The
ground beams are usually from 600mm to 1200mm for low buildings.
Deep foundations:
Ø Piles:
v Deep
foundations include piles, pile walls, diaphragm walls and caissons.
v Deep
foundations are those founding too deeply below the finished ground surface for
their base bearing capacity to be affected by surface conditions, this is
usually at depths >3m below finished ground level.
v They
include piles, piers and caissons (or) compensated foundations using deep
basements and also deep pad (or) strip foundations.
v Deep
foundations can be used to transfer the loading to a deeper, more competent
strata at depth if unsuitable soils are present near the surface.
v Piles
are relatively long, slender members that transmit foundation loads through
soil strates of low bearing capacity to deeper soil (or) rock strates having a
high bearing capacity.
v They
are used when for economic, constructional (or) soil condition considerations
it is desirable to transmit loads to strates beyond the practical reach of
shallow foundations.
v In
addition to supporting structures, piles are also used to anchor structures
against uplift forces and to assist structures in resisting lateral and
overturning forces.
v The
most expensive and the strongest type of foundation, this requires specialist
engineering to do.
v The
soil are based deep down the earth and filled with concrete to be foundation
type, a water logged area of high building ma may also require this.
v It
is the costliest hence it is used for high rise building mostly.
ü Piled
foundations can be classified according to:
Ø The type of file:
(different
structures to be supported, and different ground conditions, require different
types of resistance) and
Ø The type of construction:
(different
materials, structures and processes can be used).
Ø Types of pile:
o
End bearing
o
Friction
o
Settlement reducing
o
Tension
o
Laterally loaded
o
Piles in fill
ü Piles
are often used because adequate bearing capacity cannot be found at shallow
enough depths to support the structural loads.
ü It
is important to understand that piles get support from both end bearing and skin
friction.
ü The
proportion of carrying capacity generated by either end bearing (or) skin
friction depends on the soil conditions.
ü Piles
can be used to support various different types of structural load.
v End
bearing piles are those which terminate in hand, relatively impenetrable
material such as rock (or) very dense sand and gravel.
v They
derive most of their carrying capacity from the resistance of the stratum at
the toe of the pile.
v It
obtain a greater part of their carrying capacity by skin friction (or) adhesion.
v This
tends to occur when piles donot reach an impenetrable stratum but are driven
for some distance into a penetrable soil.
v Their
carrying capacity is derived partly from end bearing and partly from skin
friction between the embedded surface of the soil and the surrounding soil.
v These
are usually incorporated beneath the central part of a raft foundation inorder
to reduce differential settlement to an acceptable level.
v Such
piles act to reinforce the soil beneath the raft and help to prevent dishing of
the raft in the centre.
v Structures
such as tall chimneys, transmission towers can be subject to large overturning
moments and so piles are often used to resist the resulting uplift forces at
the foundation.
v In
such cases the resulting forces are transmitted to the soil along the embedded
length of the pile.
v The
resisting force can be increased in the case of based piles by under reaming.
v In
the design of tension piles the effect of radial contraction of the pile must
be taken into account as this can cause about a 10-20% reduction.
v Almost
all piled foundations are subjected to atleast some degree of horizontal
loading.
v The
magnitude of the loads in relation to the applied vertical axial loading will
generally be small and no additional design calculations will normally be
necessary.
v Traditionally
piles have been installed at an angle to the vertical in such cases providing
sufficient horizontal resistance by virtue of the component of axial capacity
of the pile which acts horizontally.
v However
the capacity of a vertical pile to resist loads applied normally to the axis,
although significantly smaller than the axial capacity of that pile, may be
sufficient to avoid the need for such ‘rating’ (or) ‘battered’ piles which are
more expensive to install.
v When
designing piles to take lateral forces it in therefore important to take this
into account.
v Piles
that pass through layers of moderately to poorly compacted fill will be
affected by negative skin friction, which produces a downward drag along the
pile shaft and therefore an additional load on the pile.
v This
occurs as the fill consolidates under its own weight.
Ø Piers:
v Piers
are foundation for carrying a heavy structural load which is constructed insitu
in a deep excavation.
Ø Caissons:
v Caissons
are a form of deep foundation which are constructed above ground level, then
sunk to the required level by excavating (or) dredging material from within the
caisson.
Ø Compensated foundations:
v Compensated
foundations are deep foundations in which the relief of stress due to
excavation is approximately balanced by the applied stress due to the
foundation.
v The
net stress applied in therefore very small.
v A
compensated foundation normally comprised a deep basement.
UNIT-II
1.
SAFETY
IN ERECTION:
v Before
erection begins a risk assessment should be carried out and a safe system of
work developed.
v The
cause of many past failures was foreseeable and could have been prevented by
proper consideration when erecting the falsework.
v Failures
often occur on fairly simply structures erected by smaller falsework
contractors, who may not employ design staff.
v Designing
falsework that can be erected safely including how striking will be achieved.
v To
ensure safety, falsework should be stable at all stages of erection and be
regularly checked.
v Erectors
should know
· Where
to start
· Whether
the equipment supplied is the same as that ordered
· At
what stage checks (or) permits are required
· Whether
checks and permits have already been carried out (or) issued
The erection of low rise buildings:
v This
highlights the principal safety objectives associated with erection of steel
work, such as the stability of part erected structure, safe lifting and placing
of steel components and safe access and working positions.
2. CONSTRUCTION MATERIALS:
v A
concrete shell also commonly called thin shell concrete structure is a
structure composed of a relatively thin shell of concrete, usually with no
interior column (or) exterior buttresses.
v The
shells are most commonly flat plates and domes, but may also take the form of
ellipsoids (or) cylindrical sections, or some combination there of.
v Concrete
is the most suitable material for construction, since it can withstand
compression forces, moreover it is workable and durable material, can be formed
to any shape you like, also it in some how cheap materials; as disadvantages.
v It
requires special care and precautions during casting otherwise it could cause
cracks and failure.
Uses:
v Most
concrete shell structures are buildings, including storage facilities,
commercial buildings and residential homes.
v Concrete
shell construction techniques are well suited for complex curves and are also
used to build boat levels (called ferro concrete).
Advantages:
v Like
the arch, the curved shapes often used for concrete shells are naturally strong
structures, allowing wide areas to be spanned without the use of internal
supports, giving an open, unobstructed interior.
v The
use of concrete as a building material reduces both materials cost and
construction costs, as concrete is relatively in expensive and easily cost into
compound curves.
v Before
during and after construction the advantages of concrete reinforce the value of
concrete construction.
v Concrete
saves money over the entire life of your structure before, during and after
construction.
v Concrete
can reduce project startup time and start to finish time compared with steel.
v Concrete
provides structural economy in many other ways too, including material costs
and improved cash flow.
v It
can also maximize marketable space and increase ROI.
v Concrete
can handle the compression stresses 10 times more than the tension and the most
of loads in our life is compression.
v Concrete
is a brittle material which gives the advantage to make a rigid structure.
v Easy
to handle over specially now there is plants that give you ready mix concrete.
Disadvantages:
v Since
concrete is a porous material, concrete domes often have issues with scaling.
v If
not treated, rain water can seep through the roof and leak into the interior of
the building.
v To
the other hand, the seamless construction of concrete domes presents air from
escaping, and can lead to buildup of condensation on the inside of the shell.
v Concrete
is weak in handling tension.
v Because
concrete is a brittle material the strength upon shear(specially at 45 degrees)
must be checked.
v It
need another material to reinforce it against excessive shear and tension.
3.
SAFETY
IN TYPICAL CIVIL STRUCTURES-DAMS:
Dams safety committee (DSC’s):
v The
DSC’s prime goal is to ensure that all prescribed dams in NSW are designed,
constructional and operated to a standard where risks to the community are
tolerably low.
v The
level of risk is determined by the likelihood and consequences of failure.
v Dam
owners are required to carefully consider the DSC’s guidance sheet on
acceptable flood capacity for dams.
v Dam
owners should ensure that the design of embankment dams (including CRFD)
clearly states the basis for design strong, the stability methodology,
assumptions on pore pressures and the factor of safety and includes calculated
predictions of the settlement behavior and states the safety against piping.
v The
design of all extreme, high and significant consequence category concrete dams
reliant on uplift relief should consider the effectiveness of the uplift relief
system and make provision for its accessibility and maintenance.
Filters/Drains:
v The
DSC is of the opinion that the design of effective drains and filters is highly
cost effective in terms of the total safety of embankment dams with all
extreme, high and significant consequence category earth fill and earth core/rock
fill dams to have fully intercepting filters.
v In
addition, seepage collection and monitoring is required in all extreme, high
and significant consequence category dams.
Conduits:
v Where
possible conduits should be embedded in the natural foundation and not located
in the embankment and no unencased metal conduits are to be used in any part of
the dam.
v All
mechanical/electrical systems essential for dam safety shall have adequate
backup provisions including backup power sources.
v Dam
design documentation requirements are outlined in the DSC’s guidance sheets on
demonstration of safety for dams and documentation and information flow over
dam life cycle.
v Partial
(or) total failure of your dam may cause extensive damage to downstream
properties, for which you the owner are likely to be held liable.
Safety surveillance:
v Safety
surveillance of a dam is a program of regular visual inspection using simple
equipment and techniques.
v It
is the most economical means of ensuring the long-term safety and survival of
your dam.
v By
regularly monitoring the condition and performance of the dam and its
surroundings, adequate warning of potentially unsafe trends will enable timely
maintenance.
UNIT-III
1.
LOCK
OUT OF MECHANICAL AND ELECTRICAL MAINTENANCE:
v This
procedure provides the fundamental components necessary for the deactivation of
the mechanical/electrical energy sources through a lockout system.
v A
lockout survey has been conducted to locate and identify all energy sources to
verify which switches (or) valves supply energy to machinery and equipment.
v Lockout
procedures are not required if equipment must be operating for proper
adjustment.
v Lockout
devices will be affixed to energy isolating devices by authorized employees.
v Lockout
devices will be affixed in a manner that will hold the energy isolating devices
from the “safe” or “off” position.
v Lockout
all energy devices by use of hasps, chains and valve covers with an assigned
individual locks.
v Before
lockout devices are removed and the energy restored to the machine (or)
equipment, the following actions will be taken.
· The
work area will be thoroughly inspected to ensure that non essential items have
been removed and that machine (or) equipment components are operational.
· The
work are will be checked to ensure that all employees have been safely
positioned (or) removed. Before the lockout device are removed, the affected
employees will be notified that the lockout devices are being removed.
· Each
lockout device will be removed from each energy isolating device by the
employee who applied the device.
Supervisor responsibilities in the
unit/branch that perform lockout practices:
ü Supervisors
are responsible for ensuring that all affected employees are trained in the
safety significance, purpose, and use of lockout practices.
ü Supervisors
are responsible for ensuring all authorized lockout employees receive the
appropriate level of training and that these employees are provided with the
proper equipment and personal protective equipment to perform the job safety.
Lockout coordinator
responsibilities:
The assigned lockout coordinator is
responsible for:
v Ensuring
equipment specific lockout practices are used.
v Ensuring
that only authorized lockout employees perform lockout operations on necessary
equipment.
v Maintaining
an inventory of all equipment in their department that requires specific
lockout practices.
v Receiving
appropriate training to become an authorized lockout employee and perform
lockout practices on equipment.
v Purchasing
(or) installing equipment and machinery to ensure that this equipment (or)
machinery has the capability to accept a
lockout device on all energy isolating devices.
v This
will include, but its not limited to, electric power disconnect devices that
can be locked only in the open(off) position, fluid control components
(eg.valves) that can be locked in the safe position, or fluid lines that have
the capability to place a mechanical barrier between a hazardous fluid and the
point where work must be performed.
v Whenever
major replacement, repair, renovation, or modification of machines (or)
equipment is to be performed, energy isolating devices for such machinery (or)
equipment shall be installed and be designed to accept a locking device so they
are capable of being locked out.
Practice:
ü The
authorized lockout employees performs the work, as well as their supervisor,
must create the work plan, written lockout practices, and physically locate and
identify all isolating devices to be sure which switches, valves, or other
energy isolating devices apply to the equipment to be locked out.
ü Employees
authorized to lockout equipment must be certain which switch (or) other energy
isolating devices apply to the equipment to be locked out.
ü Notify
all affected and other employees as necessary that a lockout is to be performed.
ü These
persons must be informed that they are not to disturb the lockout device (or)
attempt to restart the equipment until they are informed that about has been
cleared and it is safe to resume normal operations.
ü All
energy isolating devices must be locked out. Lockout the circuit breaker,
disconnect switch, or other isolating device in the open (“OFF”) position with
an assigned individual lock, and attach an identifying tag to the lock. If it
is impossible to use a lock, refer to the “practice when physical locking is
impossible” section.
ü The
equipment is now locked out.Work may now begin.
Situations involving more than one
person locking out:
ü Employees
and/or contractors must engage in a group lockout situation.
ü If
more than one employee works on the equipment, a lockout adapter suitable for
the installation of several locks must be used, enabling all workers to lockout
the machine with individual locks.
ü The
method of applying a mechanical lockout device and a tag on an energy isolating
device by an authorized employee in acceptance with established written
procedures, inorder to control hazardous energies.
ü Lockout
device-Pad locks, combination locks (or) other methods (such as disconnecting
conductor (or) removing fuses) which will effectively prevent unexpected (or) inadherent
emerging of a designated circuit (or) release of equipment (or) machinery.
ü These
devices shall not bound for the purposes-and shall include a means to indicate
the identity of the employee apply the device.
2. HAND TOOLS:
v Construction
workers are considered experts in the selection and use of hand tools, get
every year workers are injured on the job as a result of hand-tool accidents.
v Hand
tools are designed to make jobs easier and more efficient.
v Common
types of hand tools include striking tools, turning tools, metal-cutting tools,
wood cutting tools, screw drivers, pliers, knives, saws, hammers, axes,
spanners and crowbars.
v The
greatest hazards posed by these tools result from misuse and improper
maintenance.
v According
to a survey, hand tool injury rates were second highest in construction,
outranked only by agriculture.
v Poorly
maintained portable tools in construction(hand tools) prevent significant
health and safety risks to the workers using them.
v Mechanical
failure (or) loss of control when using a tool with defective parts.
v Examples
of unsafe tools are hammers with loose (or) damaged heads, screw drivers with
broken handles (or) blunt edges, chisels with mushroom head and blunt saws.
Some basic rules to prevent hazards
associated with the use of hand and power tools are:
v Examine
each tool for damage before use.
v Check
that the guards are present and secure.
v Check
wheels and blades for cracks.
v Check
electrical cards, connections, earthing. It is essential that the earth core of
the flexible cable and associated earth connections of portable electric tools
are tested regularly by a competent person to ensure continuity and strength of
the earthing.
Care and maintenance of hand tools:
v Proper
care and maintenance of hand tools will help prevent injuries to crew members
and will assist them.
Ø Hand
tools-Planes, chisels, gouges and the like absolutely require an adequate
sharpening system.
Ø A
good sharpening system for the delicate cutting edges of fine hand tools will
allow you to do two things: grind the tool to the correct shape, and hone it to
a near-perfect edge.
Ø Here
you have a few options.
Ø Perfectly
acceptable results can be achieved using grinder outfilled with a cool running
white aluminium oxide grinding wheel and a fairly simple honing system, like
the rockler’s plate glass sharpening system (or) the precision sharpening
system.
Ø If
hand tools figure prominently in your wood working, consider investing as a
more advanced sharpening system.
Ø Sharpening
hand tools is really an art form in itself, and it would be impossible to do it
justice here.
General requirements:
v A
tool maintenance procedure is one of the most important factors in any
hand-tool safety program.
v Extensively
used hand tools require careful and frequent inspection to maintain them for
safe use.
v When
hand tools are not sharpened and dressed, in efficient cutting and glancing off
material often cause injuries.
v Remove
hand tools with defective handles from service immediately.
v Personal
protective equipment must protect a person using hand tools who is exposed to
hazards, such as falling, flying, abrasive and splashing objects, or exposed to
harmful dust, fumes, mists, vapors (or) gases.
ABBREVIATIONS
UNIT-I
1)
U.S- UNITED STATES
2)
JSA- JOB SAFETY ANALYSIS
3)
CJSA-CONSTRUCTION JOB SAFETY ANALYSIS
4)
OSHA-OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION
5)
CFR-CODE OF FEDERAL REGULATIONS
6)
ICF-INSULATED CONCRETE FORMS
7)
CIS-CONSTRUCTION INDUSTRY SCHEME
8)
CDM-CLEAN DEVELOPMENT MECHANISM
9)
HAVS-HAND ARM VIBRATION SYNDROME
10)
ACM-ASBESTOS CONTAINING MATERIAL
11)
ANSI-AMERICAN NATIONAL STANDARD INSTITUTE
12)
OTM-OSHA TECHNICAL MANUAL
13)
TED-TRUNK ENCRYPTION DEVICE
14)
Df- FOUNDING DEPTH
15)
d.p.c- DAMP PROOF COURSE
UNIT-II
1)
ROI- RADIUS OF INFLUENCE
2)
DSC-DAM SAFETY COMMITTEE
3)
NSW-NEW SOUTH WALES
No comments:
Post a Comment